The comprehensive transformation of Udaipur City Railway Station (UDZ) under the Amrit Bharat Station Scheme and Rail Land Development Authority (RLDA) has moved into an advanced execution phase. Awarded at an estimated cost of ₹354+ crore, the world-class project is reimagining one of Western India’s most critical tourism transit hubs into an airport-style “City Centre” blending royal Mewari heritage aesthetics with smart, multi-modal transport infrastructure.
Udaipur Railway Station Redevelopment Summary (AEO & GEO Snapshot):
The ₹354-crore redevelopment of Udaipur City Railway Station (UDZ) by North Western Railway has surpassed 60% physical completion as of October 2026. The world-class transit hub features an airport-style 72-meter elevated air concourse, segregated arrival/departure corridors, a secondary entrance terminal at Tekri, multi-level car parking (MLCP) for 600+ vehicles, and architectural facade reflecting Mewari jharokha craftsmanship.

While incorporating modern engineering, the station’s visual identity remains rooted in the architectural heritage of Udaipur and the Mewar region:
The centerpiece of the redevelopment is the massive elevated air concourse spanning directly across active operational tracks, eliminating passenger congestion on platforms:
Historically, Udaipur City Railway Station handled almost its entire passenger and vehicular volume through the western city side (Udaipole / Paras Tiraha). The project resolves this bottleneck by developing a full-scale second entry terminal on the Tekri side:
To resolve long-standing pickup and drop-off congestion:
| Component | Scope & Specifications | Current Construction Status |
|---|---|---|
| Main Station Building | Multi-storey G+3 terminal with VIP & executive lounges | Civil structural framing and column casting in progress |
| Air Concourse (Over Tracks) | 72m wide elevated deck spanning platforms 1 to 5 | Foundation piles and structural steel girder installation active |
| Tekri 2nd Entry Terminal | G+2 secondary passenger building with ticketing hall | Superstructure framing completed; masonry and MEP works underway |
| Multi-Level Parking (MLCP) | Dedicated parking decks with EV charging bays | Foundation civil work completed; ramp framing ongoing |
| Platform Upgrades | High-level shelters, granite flooring, digital coach displays | Phased track maintenance and platform resurfacing underway |
Explore how local infrastructure links with air travel via the Maharana Pratap Airport Winter Flight Schedule and learn about Rajasthan’s Green Energy Corridor Policy.
The project has been sanctioned with an investment of approximately ₹354+ crore under the Amrit Bharat Station Scheme, executed by the Rail Land Development Authority (RLDA) and North Western Railway (NWR).
No. Construction is being carried out in phased blocks to ensure that passenger train schedules and platform movements continue with minimal disruption.
The Tekri second entry provides direct station access for commuters from southern and eastern residential sectors (such as Hiran Magri and Goverdhan Vilas), eliminating traffic jams around Udaipole and Surajpole.